QuanShun Webbing New Factory Update: Second-Floor Rooftop Progress

Nov 6,2026

Pinghu, Zhejiang, China · November 6, 2026 · QuanShun Webbing Co., Ltd.

The second-floor rooftop slab of the new QuanShun Webbing Co., Ltd. production building is now complete. As of November 6, 2026, construction crews have moved onto the finished slab and begun erecting column reinforcement and wall formwork for the level above, keeping the project on schedule.

Key Facts

  • Date of update: November 6, 2026
  • Completed: second-floor formwork, reinforcement, and rooftop concrete slab pour
  • Current stage: column cages and wall formwork above the second-floor rooftop
  • Status: on schedule

Evidence: Bracing the Second-Floor Pour

Before the slab could be poured, the production hall floor below was filled with adjustable shoring towers and formwork beams carrying the full weight of the wet concrete until it cured. The photograph below was taken by the on-site project team on November 6, 2026.

Adjustable shoring towers and formwork beams bracing the second-floor slab inside the new production hall, November 6, 2026.
Adjustable shoring towers and formwork beams bracing the second-floor slab inside the new production hall, November 6, 2026.

Along the perimeter, the second floor was wrapped in safety netting while formwork panels, plywood, and reinforcement steel coils were staged at the slab edge and lifted into position.

Second-floor perimeter under safety netting with formwork panels and rebar coils staged for the pour, November 6, 2026.
Second-floor perimeter under safety netting with formwork panels and rebar coils staged for the pour, November 6, 2026.

Rooftop Slab Complete

With the concrete cured, the second-floor rooftop now serves as a working platform. Crews are erecting the wall and column formwork that will shape the next level of the building; the finished slab, formwork edges, and staging areas are visible in the photo below.

Crews erecting wall and column formwork on the completed second-floor rooftop slab, November 6, 2026.
Crews erecting wall and column formwork on the completed second-floor rooftop slab, November 6, 2026.

Current Work Above the Rooftop

A crane now transfers formwork materials over the slab while ground teams prepare reinforcement for the columns rising out of it. Each column cage is tied and checked for spacing and alignment before the formwork closes around it — the same sequence used on the first floor, repeated one level higher.

A crane lifting formwork materials over the rooftop while column reinforcement is prepared below, November 6, 2026.
A crane lifting formwork materials over the rooftop while column reinforcement is prepared below, November 6, 2026.
A steelworker tying a column rebar cage on the finished second-floor slab, November 6, 2026.
A steelworker tying a column rebar cage on the finished second-floor slab, November 6, 2026.

Along the slab edges, wall formwork panels are already in place. Once these sections are poured, the building will take its final vertical silhouette for the first time.

Wall formwork installation underway on the second-floor rooftop, November 6, 2026.
Wall formwork installation underway on the second-floor rooftop, November 6, 2026.

Background and Implications

The new facility in Pinghu, Zhejiang, expands QuanShun Webbing's production capacity for outdoor furniture webbing, braided rope, and woven rugs. Each completed floor brings the company closer to installation of weaving lines, with expected benefits for OEM and full-container order lead times and for new product lines such as wider rugs and decorative webbing formats.

QuanShun Webbing will continue to publish dated photo updates as construction reaches each milestone. Site visits for sourcing partners can be arranged through the company's contact page once the upper levels are safe to access.

Update status: accurate as of November 6, 2026. The next scheduled milestone is the pour of the rooftop-level columns and walls.

Contact Person
Lisa
Full Name:
Lisa
Tel:

+86 15157352585

Email:
sales@webbingstyle.com
WhatsApp:
8615157352585
Address:
NO.8 Weisan Road, Zhapu town, jiaxing City. Zhejiang. China
Please send your message to us
*Email
Name
Phone
*Title
*Content
Upload
  • Only supports .rar/.zip/.jpg/.png/.gif/.doc/.xls/.pdf, maximum 20MB.
*Address